Fukushima: Kurion’s Cesium Removal System Is Clogged – Areva’s Water Decontamination System Had Not 10 But 48 Leaks!

#Fukushima I Nuke Plant: Kurion’s Cesium Removal System Is Clogged Somewhere (EX-SKF, June 12, 2011):

Part of the contaminated water treatment system being readied at Fukushima I Nuclear Power Plant is the cesium absorption tower using the technology of Kurion, a US start-up with very little information on their corporate website.

TEPCO discovered that not enough water was flowing through one of the 4 subsystems, and suspects it’s clogged up somewhere.

And a bit of new information that the Kurion’s system removes not just cesium but technetium and iodine, according to the press conference handout from TEPCO which is found below.

By the way, the number of pipe leaks in the Areva’s system was not “over 10”. Well, it was “over ten” for sure, but it was actually 48.

From Yomiuri Shinbun (11:45AM JST 6/12/2011; diagram of Kurion’s system added):

?????????????????????????????????????????????????????????????????

TEPCO announced on June 12 that the test run of the system to treat highly contaminated water at Fukushima I Nuclear Power Plant would be delayed after June 13.